Passage Data · Check a report · Use it from your AI

Haymount (Fredericksburg) ASLI V LLLP

Sewerage Systems, Rappahannock Academy, Virginia. NPDES permit VA0089125, in force until Aug 31, 2027. Last 12 months: no values over a limit. Source: EPA ECHO, Oct 22, 2026.

Reports due
About 10 days after each period: form A1 yearly
Renewal application due
Mar 4, 2027 · 180 days before expiry; your permit may set another date
Last report on file
December 2025
Oct 2024 – Sep 2025
0 values over a limit, 0 required values missing, 1 of 1 report late

Limits in force (26)

ParameterStatisticLimitMonths
Oxygen, dissolved [DO]monthly minimum≥ 6.5 mg/Lall year
BOD, 5-day, 20 deg. Cmonthly average≤ 10 mg/Lall year
BOD, 5-day, 20 deg. Cweekly maximum≤ 15 mg/Lall year
BOD, 5-day, 20 deg. Cmonthly average≤ 22 kg/dall year
BOD, 5-day, 20 deg. Cweekly maximum≤ 33 kg/dall year
BOD, 5-day, 20 deg. Cmonthly averagereport only (mg/L)all year
pHmonthly minimum≥ 6 SUall year
pHmonthly maximum≤ 9 SUall year
Solids, total suspendedmonthly average≤ 10 mg/Lall year
Solids, total suspendedweekly maximum≤ 15 mg/Lall year
Solids, total suspendedmonthly average≤ 22 kg/dall year
Solids, total suspendedweekly maximum≤ 33 kg/dall year
Solids, total suspendedmonthly averagereport only (mg/L)all year
Nitrogen, total [as N]monthly averagereport only (mg/L)all year
Nitrogen, ammonia total [as N]monthly average≤ .62 mg/Lall year
Nitrogen, ammonia total [as N]weekly average≤ .83 mg/Lall year
Nitrogen, Kjeldahl, total [as N]monthly averagereport only (mg/L)all year
Nitrite + Nitrate total [as N]monthly averagereport only (mg/L)all year
Phosphorus, total [as P]monthly averagereport only (mg/L)all year
Flow, in conduit or thru treatment plantmonthly average≤ .58 MGD (alert, not enforceable)all year
Flow, in conduit or thru treatment plantmonthly maximumreport only (MGD) (alert, not enforceable)all year
BOD, percent removal [total]monthly average minimum≥ 85 %all year
E. coligeometric mean≤ 126 #/100mLall year
Nitrogen, Total As Nmonthly average≤ 4 mg/Lall year
Phosphorus, Total As Pmonthly average≤ .3 mg/Lall year
Solids, suspended percent removalmonthly average minimum≥ 85 %all year

How strict are these limits?

Cited limits by parameter: Virginia's rules and the federal ones.

Check this month's numbers Email me before each report is due

· Save this facility as a site · Superfund sites nearby · Your permits on one board

On EPA ECHO: Facility report · DMR history

Your permit document is the final word. As JSON: /api/v1/permits/VA0089125 · MCP: https://passage-data.com/mcp