Passage Data · Check a report · Use it from your AI

Sussex Service Authority

Sewage treatment plant, Waverly, Virginia. NPDES permit VA0061310, in force until May 31, 2028. Last 12 months: over a limit 2 times (last July 2026). Source: EPA ECHO, Oct 22, 2026.

Reports due
About 10 days after each period: form M1 monthly (22 values), form M2 monthly (2 values), form Q1 quarterly (1 value), form A1 yearly, form S1 twice a year
Renewal application due
Dec 3, 2027 · 180 days before expiry; your permit may set another date
Last report on file
August 2026
Oct 2024 – Sep 2025
0 values over a limit, 0 required values missing, 0 of 31 reports late

Last 12 months (Oct 1, 2025 – Sep 30, 2026)

Period endingParameterReportedLimit
July 2026E. coli, geometric mean> 27≤ 126 #/100mL
July 2026pH, daily maximum8.2≤ 8 SU

Limits in force (32)

ParameterStatisticLimitMonths
Temperature, water deg. centigradedaily maximumreport only (deg C)all year
Oxygen, dissolved [DO]daily minimum≥ 5 mg/Lall year
pHdaily minimum≥ 6 SUall year
pHdaily maximum≤ 8 SUall year
Solids, total suspendedmonthly average≤ 20 mg/Lall year
Solids, total suspendedweekly average≤ 30 mg/Lall year
Solids, total suspendedmonthly average≤ 68 kg/dall year
Solids, total suspendedmonthly maximum≤ 100 kg/dall year
Solids, total suspendedmonthly averagereport only (mg/L)all year
Nitrogen, ammonia total [as N]monthly averagereport only (mg/L)all year
Nitrogen, Kjeldahl, total [as N]monthly average≤ 3 mg/Lall year
Nitrogen, Kjeldahl, total [as N]weekly average≤ 4.5 mg/Lall year
Nitrogen, Kjeldahl, total [as N]monthly average≤ 10 kg/dall year
Nitrogen, Kjeldahl, total [as N]weekly average≤ 15 kg/dall year
Phosphorus, total [as P]monthly averagereport only (mg/L)all year
Phosphorus, total [as P]monthly maximumreport only (mg/L)all year
Phosphorus, total [as P]monthly averagereport only (kg/mo)all year
Hardness, total [as CaCO3]monthly averagereport only (mg/L)all year
Hardness, total [as CaCO3]maximumreport only (mg/L)all year
Copper, total [as Cu]monthly average≤ 11.8 ug/Lall year
Copper, total [as Cu]weekly average≤ 11.8 ug/Lall year
Flow, in conduit or thru treatment plantdaily average≤ .9 MGD (alert, not enforceable)all year
Flow, in conduit or thru treatment plantdaily maximumreport only (MGD) (alert, not enforceable)all year
E. coligeometric mean≤ 126 #/100mLall year
Phosphorus, Total As Pannual total≤ 600 kg/yrall year
BOD, carbonaceous [5 day, 20 C]monthly average≤ 10 mg/Lall year
BOD, carbonaceous [5 day, 20 C]weekly average≤ 15 mg/Lall year
BOD, carbonaceous [5 day, 20 C]monthly average≤ 34 kg/dall year
BOD, carbonaceous [5 day, 20 C]weekly average≤ 51 kg/dall year
BOD, carbonaceous [5 day, 20 C]monthly averagereport only (mg/L)all year
BOD, carb-5 day, 20 deg C, percent removalmonthly average minimum≥ 85 %all year
Solids, suspended percent removalmonthly average minimum≥ 85 %all year

How strict are these limits?

Cited limits by parameter: Virginia's rules and the federal ones.

Check this month's numbers Email me before each report is due

· Save this facility as a site · Superfund sites nearby · Your permits on one board

On EPA ECHO: Facility report · DMR history

Your permit document is the final word. As JSON: /api/v1/permits/VA0061310 · MCP: https://passage-data.com/mcp