Sewage treatment plant, major discharger, Pacific, Missouri. NPDES permit MO0041131 expired Sep 30, 2022; its limits still apply. Last 12 months: over a limit 6 times (last September 2026), 2 required values missing, 1 of 19 reports late. Source: EPA ECHO, Oct 22, 2026.

Reports due
About 29 days after each period: outfall 001 form A monthly (16 values), outfall 001 form B quarterly (4 values), outfall SM1 form A quarterly (4 values), outfall 001 form WA yearly
Last report on file
September 2026
Oct 2024 – Sep 2025
0 values over a limit, 0 required values missing, 0 of 21 reports late

Last 12 months (Oct 1, 2025 – Sep 30, 2026)

Period endingParameterReportedLimitOver by
December 2025pH, maximum9.11≤ 9 SU—
January 2026pH, maximum9.2≤ 9 SU—
February 2026pH, maximum9.14≤ 9 SU—
March 2026Solids, suspended percent removal, monthly average minimum84≥ 85 %7%
August 2026Solids, suspended percent removal, monthly average minimum77≥ 85 %53%
September 2026Solids, suspended percent removal, monthly average minimum84≥ 85 %7%

Limits in force (26)

ParameterStatisticLimitMonthsOutfall
BOD, 5-day, 20 deg. Cweekly average≤ 45 mg/Lall year001
BOD, 5-day, 20 deg. Cmonthly average≤ 30 mg/Lall year001
pHminimum≥ 6 SUall year001
pHmaximum≤ 9 SUall year001
Solids, total suspendedweekly average≤ 45 mg/Lall year001
Solids, total suspendedmonthly average≤ 30 mg/Lall year001
Oil and grease [soxhlet extr.] tot.daily maximum≤ 15 mg/Lall year001
Oil and grease [soxhlet extr.] tot.monthly average≤ 10 mg/Lall year001
Nitrogen, total [as N]daily maximumreport only (mg/L)all year001
Nitrogen, total [as N]monthly averagereport only (mg/L)all year001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)all year001
Nitrogen, ammonia total [as N]monthly averagereport only (mg/L)all year001
Phosphorus, total [as P]daily maximumreport only (mg/L)all year001
Phosphorus, total [as P]monthly averagereport only (mg/L)all year001
Flow, in conduit or thru treatment plantdaily maximumreport only (MGD)all year001
Flow, in conduit or thru treatment plantmonthly averagereport only (MGD)all year001
E. coli7-day geometric mean≤ 630 #/100mLApr–Oct001
E. coli30-day geometric mean≤ 126 #/100mLApr–Oct001
Toxicity [acute], Ceriodaphnia dubiadaily maximumreport only (toxic)all year001
Toxicity [acute], Pimephales promelas [Fathead Minnow]daily maximumreport only (toxic)all year001
BOD, 5-day, percent removalmonthly average minimum≥ 85 %all year001
Solids, suspended percent removalmonthly average minimum≥ 85 %all year001
Nitrogen, total [as N]daily maximumreport only (mg/L)all yearSM1
Nitrogen, total [as N]monthly averagereport only (mg/L)all yearSM1
Phosphorus, total [as P]daily maximumreport only (mg/L)all yearSM1
Phosphorus, total [as P]monthly averagereport only (mg/L)all yearSM1

How strict are these limits?

Cited limits by parameter: Missouri's rules and the federal ones.

Check this month's numbers Email me before each report is due

· Save this facility as a site · Superfund sites nearby · Your permits on one board

On EPA ECHO: Facility report · DMR history

Your permit document is the final word. As JSON: /api/v1/permits/MO0041131 · MCP: https://passage-data.com/mcp