Sewage treatment plant, Norman Park, Georgia. NPDES permit GA0033600, in force until Jul 31, 2028. Last 12 months: over a limit 7 times (last September 2026), 3 of 12 reports late. Source: EPA ECHO, Oct 22, 2026.

Reports due
About 15 days after each period: form 1 monthly (43 values)
Renewal application due
Feb 2, 2028 · 180 days before expiry; your permit may set another date
Last report on file
September 2026
Oct 2024 – Sep 2025
26 values over a limit, 0 required values missing, 5 of 12 reports late

Last 12 months (Oct 1, 2025 – Sep 30, 2026)

Period endingParameterReportedLimitOver by
December 2025Nitrogen, ammonia total [as N], weekly average4 mg/L≤ 1.5 mg/L167%
June 2026Flow, in conduit or thru treatment plant, weekly average.294 MGD≤ .25 MGD18%
June 2026Solids, suspended percent removal, minimum81 %≥ 85 %27%
August 2026Nitrogen, total [as N], monthly average43.9 mg/L≤ 20 mg/L120%
August 2026Nitrogen, total [as N], weekly average43.9 mg/L≤ 30 mg/L46%
September 2026Nitrogen, total [as N], monthly average< 31.7 mg/L≤ 20 mg/L58%
September 2026Nitrogen, total [as N], weekly average< 37.4 mg/L≤ 30 mg/L25%

Limits in force (53)

ParameterStatisticLimitMonths
Oxygen, dissolved [DO]minimum≥ 5 mg/Lall year
BOD, 5-day, 20 deg. Cmonthly average≤ 20 mg/LMay–Dec
BOD, 5-day, 20 deg. Cmonthly average≤ 25 mg/LJan–Apr
BOD, 5-day, 20 deg. Cweekly average≤ 30 mg/LMay–Dec
BOD, 5-day, 20 deg. Cweekly average≤ 37.5 mg/LJan–Apr
BOD, 5-day, 20 deg. Cmonthly average≤ 33 lb/dMay–Dec
BOD, 5-day, 20 deg. Cmonthly average≤ 42 lb/dJan–Apr
BOD, 5-day, 20 deg. Cweekly average≤ 42 lb/dMay–Dec
BOD, 5-day, 20 deg. Cweekly average≤ 52 lb/dJan–Apr
BOD, 5-day, 20 deg. Cmonthly averagereport only (mg/L)all year
BOD, 5-day, 20 deg. Cweekly averagereport only (mg/L)all year
BOD, 5-day, 20 deg. Cmonthly averagereport only (lb/d)all year
BOD, 5-day, 20 deg. Cweekly averagereport only (lb/d)all year
pHminimum≥ 6 SUMay–Dec
pHminimum≥ 6 SUJan–Apr
pHmaximum≤ 8 SUMay–Dec
pHmaximum≤ 8.5 SUJan–Apr
Solids, total suspendedmonthly average≤ 30 mg/Lall year
Solids, total suspendedweekly average≤ 45 mg/Lall year
Solids, total suspendedmonthly average≤ 50 lb/dall year
Solids, total suspendedweekly average≤ 63 lb/dall year
Solids, total suspendedmonthly averagereport only (mg/L)all year
Solids, total suspendedweekly averagereport only (mg/L)all year
Solids, total suspendedmonthly averagereport only (lb/d)all year
Solids, total suspendedweekly averagereport only (lb/d)all year
Nitrogen, total [as N]monthly average≤ 20 mg/Lall year
Nitrogen, total [as N]weekly average≤ 30 mg/Lall year
Nitrogen, total [as N]monthly average≤ 33.4 lb/dall year
Nitrogen, total [as N]weekly average≤ 41.7 lb/dall year
Nitrogen, organic total [as N]monthly averagereport only (mg/L)all year
Nitrogen, ammonia total [as N]monthly average≤ 1 mg/LMay–Dec
Nitrogen, ammonia total [as N]monthly average≤ 2.1 mg/LJan–Apr
Nitrogen, ammonia total [as N]weekly average≤ 1.5 mg/LMay–Dec
Nitrogen, ammonia total [as N]weekly average≤ 3.2 mg/LJan–Apr
Nitrogen, ammonia total [as N]monthly average≤ 1.7 lb/dMay–Dec
Nitrogen, ammonia total [as N]monthly average≤ 3.5 lb/dJan–Apr
Nitrogen, ammonia total [as N]weekly average≤ 2.1 lb/dMay–Dec
Nitrogen, ammonia total [as N]weekly average≤ 4.4 lb/dJan–Apr
Nitrogen, Kjeldahl, total [as N]monthly averagereport only (mg/L)all year
Nitrite + Nitrate total [as N]monthly averagereport only (mg/L)all year
Phosphorus, total [as P]monthly average≤ 5 mg/Lall year
Phosphorus, total [as P]weekly average≤ 7.5 mg/Lall year
Phosphorus, total [as P]monthly average≤ 8.3 lb/dall year
Phosphorus, total [as P]weekly average≤ 10.4 lb/dall year
Phosphate, ortho [as P]monthly averagereport only (mg/L)all year
Flow, in conduit or thru treatment plantmonthly average≤ .2 MGDall year
Flow, in conduit or thru treatment plantweekly average≤ .25 MGDall year
Chlorine, total residualdaily maximum≤ .01 mg/Lall year
E. colimonthly geometric mean≤ 126 #/100mLall year
E. coliweekly geometric mean≤ 410 #/100mLall year
Solids, sludge, total, dry weightmonthly totalreport only (dry ton)all year
BOD, 5-day, percent removalminimum≥ 85 %all year
Solids, suspended percent removalminimum≥ 85 %all year

How strict are these limits?

Cited limits by parameter: Georgia's rules and the federal ones.

Check this month's numbers Email me before each report is due

· Save this facility as a site · Superfund sites nearby · Your permits on one board

On EPA ECHO: Facility report · DMR history

Your permit document is the final word. As JSON: /api/v1/permits/GA0033600 · MCP: https://passage-data.com/mcp