Clear Creek Skiing Corp

Sewerage Systems, Georgetown, Colorado. NPDES permit CO0040835 expired Sep 30, 2016; its limits still apply. Last 12 months: no values over a limit. Source: EPA ECHO, Oct 22, 2026.

Reports due
About 28 days after each period: outfall 001 form A monthly (14 values), outfall 001 form Q quarterly (8 values), outfall 300 form I monthly (10 values)
Last report on file
August 2026
Oct 2024 – Sep 2025
0 values over a limit, 0 required values missing, 0 of 28 reports late

Limits in force (54)

ParameterStatisticLimitMonthsOutfall
BOD, 5-day, 20 deg. C30-day average≤ 30 mg/Lall year001
BOD, 5-day, 20 deg. Cmaximum 7-day average≤ 45 mg/Lall year001
pHminimum≥ 6.5 SUall year001
pHmaximum≤ 9 SUall year001
Solids, total suspended30-day average≤ 30 mg/Lall year001
Solids, total suspendedmaximum 7-day average≤ 45 mg/Lall year001
Nitrogen, total [as N]30-day averagereport only (mg/L)all year001
Nitrogen, total [as N]daily maximumreport only (mg/L)all year001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Jun001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Aug001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Sep001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Jul001
Nitrogen, ammonia total [as N]30-day average≤ 63 mg/LMar001
Nitrogen, ammonia total [as N]30-day average≤ 62 mg/LJan001
Nitrogen, ammonia total [as N]30-day average≤ 69 mg/LFeb001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Oct001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Nov001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)May001
Nitrogen, ammonia total [as N]30-day averagereport only (mg/L)Apr001
Nitrogen, ammonia total [as N]30-day average≤ 54 mg/LDec001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Jun001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Aug001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Sep001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Jul001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Mar001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Jan001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Feb001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Oct001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Nov001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)May001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Apr001
Nitrogen, ammonia total [as N]daily maximumreport only (mg/L)Dec001
Phosphorus, total [as P]30-day averagereport only (mg/L)all year001
Phosphorus, total [as P]daily maximumreport only (mg/L)all year001
Oil and greaseinstantaneous maximum≤ 10 mg/Lall year001
Flow, in conduit or thru treatment plant30-day average≤ .03 MGDall year001
Flow, in conduit or thru treatment plantdaily maximumreport only (MGD)all year001
Chlorine, total residual30-day average≤ .11 mg/Lall year001
Chlorine, total residualdaily maximum≤ .3 mg/Lall year001
E. coli30-day average≤ 1920 #/100mLall year001
E. colidaily maximum≤ 3840 #/100mLall year001
BOD, 5-day, percent removalmonthly average minimum≥ 85 %all year001
Solids, suspended percent removalmonthly average minimum≥ 85 %all year001
Oil and grease visualinstantaneous maximumreport only (N=0;Y=1)all year001
Plant capacity fact. percent of capacity30-day averagereport only (%)all year300
Plant capacity fact. percent of capacity30-day averagereport only (%)all year300
BOD, 5-day, 20 deg. C30-day averagereport only (mg/L)all year300
BOD, 5-day, 20 deg. Cmaximum 7-day averagereport only (mg/L)all year300
BOD, 5-day, 20 deg. C30-day averagereport only (lb/d)all year300
BOD, 5-day, 20 deg. Cmaximum 7-day averagereport only (lb/d)all year300
Solids, total suspended30-day averagereport only (mg/L)all year300
Solids, total suspendedmaximum 7-day averagereport only (mg/L)all year300
Flow, in conduit or thru treatment plant30-day averagereport only (MGD)all year300
Flow, in conduit or thru treatment plantdaily maximumreport only (MGD)all year300

How strict are these limits?

Cited limits by parameter: Colorado's rules and the federal ones.

Check this month's numbers Email me before each report is due

· Save this facility as a site · Superfund sites nearby · Your permits on one board

On EPA ECHO: Facility report · DMR history

Your permit document is the final word. As JSON: /api/v1/permits/CO0040835 · MCP: https://passage-data.com/mcp